TIER 1 — URGENT Unresolved
Violation related to Nitrate
When: September 1, 2025 – September 30, 2025Rule: Surface Water Treatment RuleVerify on EPA.gov TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: July 2, 2025 – September 18, 2025Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Monitoring violation
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2025 – August 12, 2025Rule: Total Coliform RuleEnforcement: Resolving — corrective action underway
TIER 3 Unresolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2025 – September 30, 2025Rule: Stage 2 DBPRVerify on EPA.gov TIER 3 Unresolved
Exceeded the MCL for disinfection byproducts
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2025 – September 30, 2025Verify on EPA.gov TIER 3 Unresolved
Exceeded the MCL for disinfection byproducts
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2025 – September 30, 2025Verify on EPA.gov TIER 3 Unresolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2025 – September 30, 2025Rule: Stage 2 DBPRVerify on EPA.gov TIER 2 Unresolved
Treatment Technique Violation
When: July 1, 2025 – September 30, 2025Rule: Stage 1 DBPRVerify on EPA.gov TIER 3 Resolved
Failed to complete routine monitoring
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: June 1, 2025 – June 30, 2025Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Unresolved
Failed to complete routine monitoring
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: May 1, 2025 – May 31, 2025Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Unresolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: May 1, 2025 – May 31, 2025Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 1 — URGENT Unresolved
Violation related to Nitrate
When: May 1, 2025 – May 31, 2025Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 1 — URGENT Unresolved
Violation related to Nitrate
When: May 1, 2025 – May 31, 2025Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Resolved
Exceeded the MCL for disinfection byproducts
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: April 1, 2025 – June 30, 2025Enforcement: Resolving — corrective action underway
TIER 3 Unresolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: April 1, 2025 – June 30, 2025Rule: Stage 2 DBPREnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Resolved
Exceeded the MCL for disinfection byproducts
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: April 1, 2025 – June 30, 2025Enforcement: Resolving — corrective action underway
TIER 2 Unresolved
Treatment Technique Violation
When: April 1, 2025 – June 30, 2025Rule: Stage 1 DBPREnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Unresolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: April 1, 2025 – June 30, 2025Rule: Stage 2 DBPREnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Unresolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: February 1, 2025 – February 28, 2025Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Unresolved
Exceeded the MCL for disinfection byproducts
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: January 1, 2025 – March 31, 2025Enforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 2 Unresolved
Treatment Technique Violation
When: January 1, 2025 – March 31, 2025Rule: Stage 1 DBPREnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Resolved
Reporting violation
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: October 17, 2024 – March 11, 2025Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 2 Resolved
Treatment technique violation
When: October 17, 2024 – March 11, 2025Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: October 1, 2024 – December 31, 2024Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Unresolved
Exceeded the MCL for disinfection byproducts
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: October 1, 2024 – December 31, 2024Enforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Unresolved
Exceeded the MCL for disinfection byproducts
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: October 1, 2024 – December 31, 2024Enforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Unresolved
Disinfection byproduct treatment technique failure
When: September 22, 2024Rule: Ground Water RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 1 — URGENT Unresolved
Violation related to Nitrate
When: September 1, 2024 – September 30, 2024Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Unresolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: September 1, 2024 – September 30, 2024Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: August 30, 2024 – October 10, 2024Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Unresolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: August 1, 2024 – August 31, 2024Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 1 — URGENT Unresolved
Violation related to Nitrate
When: August 1, 2024 – August 31, 2024Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 1 — URGENT Unresolved
Violation related to Nitrate
When: July 1, 2024 – July 31, 2024Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: July 1, 2024 – September 30, 2024Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Resolved
Exceeded the MCL for disinfection byproducts
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2024 – September 30, 2024Enforcement: Resolving — corrective action underway
TIER 3 Unresolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2024 – July 31, 2024Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Resolved
Failed to conduct Level 2 Assessment
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: June 30, 2024 – July 31, 2024Rule: Stage 2 DBPREnforcement: Formal — state order issued
TIER 3 Unresolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: June 1, 2024 – June 30, 2024Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 1 — URGENT Unresolved
Violation related to Nitrate
When: June 1, 2024 – June 30, 2024Rule: Surface Water Treatment RuleEnforcement: Informal — resolved cooperativelyVerify on EPA.gov TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: May 31, 2024 – July 10, 2024Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: May 31, 2024 – July 10, 2024Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: April 1, 2024 – June 30, 2024Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: January 1, 2024 – March 31, 2024Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: November 8, 2023 – November 15, 2023Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Monitoring violation
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: November 1, 2023 – December 18, 2023Rule: Total Coliform RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: November 1, 2023 – November 30, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: October 1, 2023 – December 31, 2023Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Resolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: October 1, 2023 – December 31, 2023Rule: Stage 1 DBPREnforcement: Resolving — corrective action underway
TIER 3 Resolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2023 – July 31, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed to complete routine monitoring
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2023 – July 31, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2023 – September 30, 2023Rule: Stage 1 DBPREnforcement: Resolving — corrective action underway
TIER 1 — URGENT Resolved
Violation related to Nitrate
When: July 1, 2023 – July 31, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: July 1, 2023 – September 30, 2023Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Resolved
Failed to complete routine monitoring
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: June 1, 2023 – June 30, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: June 1, 2023 – June 30, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: May 1, 2023 – May 31, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed to complete routine monitoring
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: May 1, 2023 – May 31, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: April 1, 2023 – April 30, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed to complete routine monitoring
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: April 1, 2023 – April 30, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: April 1, 2023 – June 30, 2023Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Resolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: March 1, 2023 – March 31, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed to complete routine monitoring
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: March 1, 2023 – March 31, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Monitoring violation
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: January 1, 2023 – April 24, 2023Rule: Total Coliform RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed to complete routine monitoring
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: January 1, 2023 – January 31, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: January 1, 2023 – March 31, 2023Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Resolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: January 1, 2023 – January 31, 2023Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Monitoring / Reporting Violation
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: January 1, 2023 – April 24, 2023Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: January 1, 2023 – March 31, 2023Rule: Stage 1 DBPREnforcement: Resolving — corrective action underway
TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: December 4, 2022 – December 7, 2022Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: December 4, 2022 – December 7, 2022Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Surface water treatment technique failure
When: October 2, 2022 – February 22, 2023Enforcement: Resolving — corrective action underway
TIER 3 Resolved
Exceeded the MCL for disinfection byproducts
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: October 1, 2022 – December 31, 2022Enforcement: Resolving — corrective action underway
TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: October 1, 2022 – December 31, 2022Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Resolved
Failed to issue ongoing public notification
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: October 1, 2022 – December 15, 2022Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Monitoring violation
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: September 1, 2022 – November 2, 2022Rule: Total Coliform RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: September 1, 2022 – September 30, 2022Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed to complete routine monitoring
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: September 1, 2022 – September 30, 2022Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: August 28, 2022 – July 1, 2022Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: July 1, 2022 – September 30, 2022Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Resolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2022 – September 30, 2022Rule: Stage 1 DBPREnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2022 – September 30, 2022Rule: Stage 1 DBPREnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed to conduct Level 2 Assessment
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: June 30, 2022 – October 17, 2022Rule: Stage 2 DBPREnforcement: Formal — state order issued
TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: June 3, 2022 – February 9, 2024Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Monitoring violation
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: June 1, 2022 – August 24, 2022Rule: Total Coliform RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: June 1, 2022 – June 30, 2022Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed to complete routine monitoring
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: June 1, 2022 – June 30, 2022Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: May 29, 2022 – July 1, 2022Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: April 1, 2022 – June 30, 2022Rule: Stage 2 DBPREnforcement: Resolving — corrective action underway
TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: April 1, 2022 – June 30, 2022Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Resolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: April 1, 2022 – June 30, 2022Rule: Stage 1 DBPREnforcement: Resolving — corrective action underway
TIER 3 Resolved
Exceeded the MCL for disinfection byproducts
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: April 1, 2022 – June 30, 2022Enforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: April 1, 2022 – June 30, 2022Rule: Stage 2 DBPREnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: April 1, 2022 – June 30, 2022Rule: Stage 1 DBPREnforcement: Resolving — corrective action underway
TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: March 19, 2022 – February 16, 2022Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: March 2, 2022 – July 10, 2024Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Monitoring violation
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: March 1, 2022 – April 13, 2022Rule: Total Coliform RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Disinfection byproduct treatment technique failure
When: February 17, 2022 – July 10, 2024Rule: Ground Water RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Monitoring violation
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: January 1, 2022 – February 25, 2022Rule: Total Coliform RuleEnforcement: Resolving — corrective action underway
TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: January 1, 2022 – March 31, 2022Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Resolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: January 1, 2022 – March 31, 2022Rule: Stage 1 DBPREnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed Level 2 Assessment under Revised Total Coliform Rule
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: January 1, 2022 – March 31, 2022Rule: Stage 1 DBPREnforcement: Resolving — corrective action underway
TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: October 1, 2021 – December 31, 2021Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Resolved
Failed to conduct Level 2 Assessment
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: August 18, 2021 – March 8, 2022Rule: Stage 2 DBPREnforcement: Formal — state order issued
TIER 3 Resolved
Missed required monitoring deadline
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: August 1, 2021 – August 31, 2021Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed to complete routine monitoring
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: August 1, 2021 – August 31, 2021Rule: Surface Water Treatment RuleEnforcement: Resolving — corrective action underway
TIER 2 Unresolved
Exceeded the Maximum Contaminant Level (running average)
When: July 1, 2021 – September 30, 2021Rule: Stage 2 DBPREnforcement: Formal — state order issuedVerify on EPA.gov TIER 3 Resolved
Monitoring Violation
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: July 1, 2021 – July 31, 2021Rule: Total Coliform RuleEnforcement: Resolving — corrective action underway
TIER 3 Resolved
Failed to conduct Level 2 Assessment
This is a paperwork/process violation — it does not mean a contaminant was detected at unsafe levels.
When: May 15, 2021 – March 8, 2022Rule: Stage 2 DBPREnforcement: Formal — state order issued